Accelerator Report: The LHC commissioning is well on track, but challenges lie ahead
Last week, on 19 March, the first beam-based physics of the year began when protons from the PS hit the n_TOF target, producing the neutrons required for the n_TOF experiments. On that same day, physics was also scheduled to start in the PS East Area, but had to be delayed after an issue with a collimator in one of the four East Area beamlines was identified: the collimator was found to be partially closed and obstructing the beam path.
Collimators are key components used to remove unwanted halo particles from the beam. They consist of movable parts that can be adjusted electro-mechanically to set the beam’s aperture. In this case, the faulty collimator required replacement.
Under the coordination of the Experimental Areas (BE-EA) group, a team of experts from various domains quickly devised a plan for the replacement. However, accessing the collimator required the removal of the thick concrete shielding blocks above the beamline.
Initial estimates projected a delay of three to four days to the start of physics in the East Area, with hopes of resuming beam operations over the weekend. Thanks to the efficiency and excellent collaboration of the teams involved, the collimator was successfully replaced and the shielding reinstated in the early afternoon of 22 March. Beam for physics was delivered to the East Area at 4 p.m. that same day, just in time for the weekend and only two days behind the original schedule.
On the left: the collimator that has been replaced. On the right: work in progress to remove the roof shielding to access the collimator.
(Image: CERN)
Meanwhile, beam commissioning in the SPS is progressing well. A high-intensity LHC-type beam, containing more protons per bunch than usual, is currently being used to “scrub” the vacuum chamber. This scrubbing process helps reduce the emission of secondary electrons, which in turn lowers the formation of electron clouds. Minimising electron-cloud effects is essential for stable beam conditions and quality when the LHC-type beam is eventually delivered to the LHC.
In parallel, SPS experts have been setting up the beam and its slow extraction for the SPS North Area. Slow extraction is a technique in which the accelerated beam is gradually extracted from the SPS over millions of turns. During each turn, only a small fraction of the beam is extracted, allowing the entire extraction process to span approximately 4.5 seconds.
In the coming weeks, beamline physicists will use this extracted beam to set up the various beamlines in the North Area, delivering the beam to the experiments. Physics in the North Area is scheduled to begin on 14 April.
In my previous report, I mentioned the presence of a small vacuum leak in the SPS. The opening and closing of this leak appear to be synchronised with the pulsing of the magnets, but the leak remains too small to be precisely located, making it impossible to determine with certainty which magnet needs to be replaced.
Depending on how one looks at it, the leak has fortunately or unfortunately not evolved; it remains present but stable. As time goes on, however, it is increasingly likely that a one-day stop during the physics run may be required to replace a magnet. That said, this decision will depend on whether the leak worsens and becomes easier to localise. We continue to monitor the situation closely and will keep you informed as it develops.
On the LHC side, testing of all power converters, electrical circuits, magnets and other systems is progressing well and is even slightly ahead of schedule. On the machine side all remains on track for the first beam injection, originally planned for 4 April.
However, we recently received some unfortunate news from the ATLAS experiment. A water leak was discovered in the cooling system of their argon calorimeter (detector), which now requires repair. To access the affected components, the detector must be opened on one side, which is usually a complex and time-consuming operation.
Despite the complexity of the operation, the resulting delay to the overall LHC schedule is expected to be limited to just two weeks. This situation highlights a key difference between the LHC and the rest of the accelerator complex: in the LHC, the experiments are fully integrated into the machine itself, meaning that an intervention in ATLAS directly affects the ability to inject and circulate beam. In contrast, experiments in the injector complex operate on separate beamlines and are therefore independent of accelerator operation.
The LHC machine teams are working closely with the ATLAS collaboration to develop a plan that makes most efficient use of the available time and keeps the delay to a minimum.
Originally, first beam was scheduled for 4 April, comfortably ahead of the Easter weekend. Many were pleased, as LHC beam commissioning has traditionally, though unintentionally, coincided with Easter. Now, if the two-week delay holds, the 2025 commissioning may once again fall during the Easter weekend. Have we discovered a new constant of nature? We’ll see in the coming days when the details become clearer…
anschaef
Thu, 03/27/2025 - 11:41
Byline
Rende Steerenberg
Publication Date
Thu, 03/27/2025 - 11:39